Skip Navigation

Joondanna Zone Substation

In response to rapid redevelopment of the Osborne Park industrial area, Western Power is currently planning the construction of a new 132 kV zone substation on the corner of Albert Street and Roberts Road in Osborne Park. This new substation will enable Western Power to continue providing safe, reliable and efficient power supply to the areas of Osborne Park, Tuart Hill and Joondanna.

Project Update

Construction of the new Joondanna zone substation will take place in three stages:

Stage One: Removal of existing unused site premises

In order to start works on the new substation site, the existing unused premises must first be removed - note that analysis of these unused premises has identified the existence of asbestos materials.

To ensure the safe and thorough removal of asbestos materials on the site, Western Power has engaged the services of Parsons Brinckerhoff; industry experts with accreditation from the National Association of Testing Authorities (NATA), who will monitor the works to guarantee they are carried out in accordance with Western Australia's Work Safe regulations, and the National Occupational Health and Safety Commission Code of Practice and Australian Standards.

Works are expected to take place around mid 2009, with further information updates to be provided soon.

Stage Two: Building & connecting the new Substation

Works for the new 132 kV substation will involve; construction of two new buildings for housing equipment, the installation of a new transformer, plus the installation of other electrical equipment for use by the new substation.

The new substation will then be connected to the existing transmission network via underground power cables buried along Gordon Road East, Albert Street and McDonald Street; with two new transition poles being installed to connect the new cables back up to the existing overhead transmission power lines. Further works in the area will include;

  • upgrading some existing poles,
  • installing new poles,
  • adding stay-wires to secure some wooden poles, and
  • relocating some of the existing over head distribution power lines to run underground.

Stage Three: Visual impact management & reinstatement works

Once the underground cable has been installed, the overhead section of the transmission line and all redundant poles between the two transition poles will be removed.

To ensure public safety and security of the substation, a 3.5m high concrete wall surrounding the perimeter of the site will be constructed, and finished with an anti-graffiti coating.

Reinstatement works of any flora, curbing or road impacts that may occur as a result of the Western Power works will also be finalised during this period.

Traffic Disruptions

Western Power and its contractors will ensure all works are carried out in a safe manner, and will manage traffic flow in the area. Information outlining specific road closures will be communicated as once details are confirmed.

Community Engagement

Western Power will keep the community and key stakeholders informed regarding the progress of this project by distributing project brochures, posting public notices in local newspapers and providing updated project information via the Western Power website.

Location

Joondanna substation map

Project timeline *

June 2009 Stage 1 - Site works complete
Early 2010 Stage 2 - Building & connecting the substation to the network complete
Mid 2010 Stage 3 - Visual Impact Management & Reinstatement works complete

*subject to change

Key facts

Contact us

For more information, please contact Project Officer Scott Varvell on 9326 4517.

Subscribe to Projects RSS Feed

To view PDF files you will need Adobe Acrobat Reader.

Customers with accessibility issues.

Page update on 23 June 2009