Kojonup to Albany transmission line
GHD's full report is now available. It explains the sustainability assessment process and provides a detailed numeric comparison of the corridor options showing why one option is preferred over the others.

Bentley zone substation
Construction of the new 132,000 volt (132 kV) zone substation in McKay Street, Bentley, south of the Curtin University Campus has been completed.

Eastern terminal switchyard
Western Power is proposing to construct a new terminal switchyard on a 20 hectare area of land in the Kalamunda, Gosnells and/or Mundaring area and is currently looking for a suitable site.

View electricity consumption

Media

02 Jul 08

Eastern Terminal submission period extended
The extension will ensure community members, local government and other interest groups have ample opportunity to express their opinion.


More updates

Vegetation close to powerlines